Friday, 5 September 2014

HusCompagniet - Second meeting

So, we found and reserved a ground. Now it was time to find out what exactly we could build on it. We had a think about which company we should ultimately choose to have a meeting with again, and because he had not heard anything from Eurodan Huse since the first meeting, plus because HusCompagniet had been very helpful, we chose to book a meeting with HusCompagniet in July 2014.

For the meeting, we went through almost the exact same things we discussed in our first meeting, but we decided (after being recommended by many people we had spoken to) that we would add a patio overhang (overdækket terrace). As standard, this feature comes with galvanized tubes to support the overhang, which doesn't look so nice. Instead, we decided to use brick supporting columns, which look much nicer. In all, this extension cost 39,700dkk. We also discussed using district heating, triple glazed windows and extra insulation instead of a geothermal heat pump in the garden, which was cheaper by around 50,000dkk. This was no problem for HusCompagniet to use.

As the salesman knew that we had spoken to Eurodan, he offered to make us a good deal. After a bit of discussion, we managed to get the extra 40,000 dkk we added to our HTH budget for free! Only condition was that we had to use all of it, so we wouldn't get the money back if we didn't use it all. But that was fine with us, and effectively meant that we got the patio overhang for free! And overall, the estimated house price was 1,946,740dkk, so actually a bit lower than the first meeting!

At the end of the meeting, we had a huge decision to make. The contract for the house was fully prepared and ready to sign, if we wanted to go with HusCompagniet. Shall we sign the contract now, and not go home and think about it? Will the bank be OK without us double checking with them first? We decided to take the plunge, and sign there and then!!! Scary!!! We had just signed our lives away on our dream house.

Straight away, we got an estimated moving in date... The 24th February 2014, and building work would begin some time in October 2014, amazing!

Next steps? Start talking about house drawings, final placement on the ground, HTH units, electrical installation.... Plus many many others things.