Thursday, 2 October 2014

The project plan for the build

In the last week of September, we got the building schedule from the project manager at HusCompagniet. Now we know when to go out to the ground, and see something happening. Finally, building work is about to begin. Can't wait!

Here's the plan.

Week 40, 41 & 42 Foundation
Week 43 Inner walls go up
Week 44 45 46 47 Carpenter
Week 48 First fix electrical and plumbing
Week 48 Roof tiles go on
Week 49 Internal brickwork
Week 49, 50 & 51 External brickwork
Week 50 & 51 Ceilings
Week 2  3 Laying floor tiles
Week 4 Painting
Week 5 & 6 Kitchen & bathroom fitting
Week 7 Flooring
Week 8 Energy measurement 
Week 9 Delivery and hand over 

Bring on week 9 next year!!