Here's the plan.
Week 40, 41 & 42 Foundation
Week 43 Inner walls go up
Week 44 45 46 47 Carpenter
Week 48 First fix electrical and plumbing
Week 48 Roof tiles go on
Week 49 Internal brickwork
Week 49, 50 & 51 External brickwork
Week 50 & 51 Ceilings
Week 2 3 Laying floor tiles
Week 4 Painting
Week 5 & 6 Kitchen & bathroom fitting
Week 7 Flooring
Week 8 Energy measurement
Week 9 Delivery and hand over
Bring on week 9 next year!!